041-jpn-projects-suffolk-park.jpg

Suffolk Park

Bury St Edmunds

A major allocated employment site with outline planning consent for up to 2 million sq ft of B1 and B8 uses.

The infrastructure contract included the creation of a new spine road, off site reinforcement works, new incoming major services for Gas, Water, Electric, Fibre & BT.

Client – Jaynic
Architect – PRC Architectural
Structural Engineer – Richard Jackson
Utilities – Peter Brett Associates
Contractor – Jackson Civils
Civils – £3m
Utilities – £8m
Duration – 26 Weeks
Form – JCT 2011 Design and Build

 

 
042-jpn-projects-haverhill-research-park.jpeg

Haverhill Research Park

A 30 acre site, assembled and master-planned to create a 450,000 sq ft Business / R&D Park, Hotel, Day Nursery, Pub/Restaurant and 150 Residential Units.

 

 
043-jpn-projects-stanton-masterplan.png

Stanton Masterplan

A new business park for up to 1.75 million sq ft of floorspace creating a significant number of new jobs.

All HGV traffic currently going through Stanton to the existing Shepherd’s Grove West industrial estate will be able to enter Shepherd’s Grove via a new roundabout junction on the A143 and a new access road into the heart of the area. This offers a new fully serviced road network for local business and residential plots.

A new and attractive residential development of between 265 and 380 dwellings with improved pedestrian and cycle access to Stanton and the existing primary school, healthcare and shopping facilities